02/08/12 Paving of driveway completed
01/08/12 Paving of driveway commenced
01/08/12 Rear hallway tiled
30/07/12 PCI
26/07/12 Driveway poured
20/07/12 Rangehood installed
19/07/12 Door handles installed
17/07/12 Driveway dug out
13/07/12 Grout complete to flooring. Shower screens installed
09/07/12 Tiles laid to rest of the house
04/07/12 Shelves installed to pantry/linen/wardrobes. Pavers for driveway delivered
03/07/12 Plumbing done
02/07/12 Electrical done
01/07/12 Grouting finished in bathrooms
30/06/12 Kitchen benchtop installed
28/06/12 Painting started
21/06/12 Tiler's started all wet areas and alfresco
19/06/12 Kitchen and bathroom/ensuite cabinets installed
12/06/12 Gyprock done
09/06/12 Lock up!
09/05/12 Air conditioning rough in done
08/05/12 Eaves commenced
05/05/12 Roof completed
04/05/12 Roof commenced
01/05/12 Brickwork complete
05/04/12 Brick laying continues
04/04/12 Brick laying commenced
03/04/12 Bricks delivered to the site
02/04/12 Plumber began rough in
30/03/12 Frame work complete
29/03/12 Frame work started
28/03/12 Frames delivered to site
26/03/12 Met with SS.
21/03/12 Concrete poured - we have a slab!!!!
20/03/12 Temporary fence erected
19/03/12 Waffle pods and reo installed
16/03/12 Plumber installed internal pipes
15/03/12 Footings drilled and filled and border for slab put in and dug out for drop edge beam
12/03/12 All weather access gravel put down
09/03/12 Silt fence & waste disposal area put up
07/03/12 Site excavated
07/03/12 Administration complete!!!
17/02/12 Finance approval received
02/02/12 Construction drawings signed
05/01/12 Construction Certificate received
05/01/12 Permit received
20/12/11 Kitchen Upgrades
06/12/11 Electrical Selection
21/11/11 Permit Ordered
04/11/11 Land Settlement
03/11/11 Colour Selection appointment
02/11/11 Engineering Drawings Signed
31/10/11 BASIX Approval
27/10/11 Water Board Approval
20/10/11 Building Contract appointment & building contract signed
04/10/11 Tender signed
29/09/11 Tender Appointment
22/09/11 Soil report
19/09/11 Contour survey conducted
12/09/11 Initial deposit