Timeline of our build

02/08/12    Paving of driveway completed
01/08/12    Paving of driveway commenced
01/08/12    Rear hallway tiled
30/07/12    PCI
26/07/12    Driveway poured
20/07/12    Rangehood installed
19/07/12    Door handles installed
17/07/12    Driveway dug out
13/07/12    Grout complete to flooring.  Shower screens installed
09/07/12    Tiles laid to rest of the house
04/07/12    Shelves installed to pantry/linen/wardrobes.  Pavers for driveway delivered
03/07/12    Plumbing done
02/07/12    Electrical done
01/07/12    Grouting finished in bathrooms
30/06/12    Kitchen benchtop installed
28/06/12    Painting started
21/06/12    Tiler's started all wet areas and alfresco
19/06/12    Kitchen and bathroom/ensuite cabinets installed
12/06/12    Gyprock done
09/06/12    Lock up!
09/05/12    Air conditioning rough in done
08/05/12    Eaves commenced
05/05/12    Roof completed
04/05/12    Roof commenced
01/05/12    Brickwork complete
05/04/12    Brick laying continues
04/04/12    Brick laying commenced
03/04/12    Bricks delivered to the site
02/04/12    Plumber began rough in
30/03/12    Frame work complete
29/03/12    Frame work started
28/03/12    Frames delivered to site
26/03/12    Met with SS. 
21/03/12    Concrete poured - we have a slab!!!!
20/03/12    Temporary fence erected
19/03/12    Waffle pods and reo installed
16/03/12    Plumber installed internal pipes
15/03/12    Footings drilled and filled and border for slab put in and dug out for drop edge beam
12/03/12    All weather access gravel put down
09/03/12    Silt fence & waste disposal area put up
07/03/12    Site excavated
07/03/12    Administration complete!!!
17/02/12    Finance approval received
02/02/12    Construction drawings signed
05/01/12    Construction Certificate received
05/01/12    Permit received
20/12/11    Kitchen Upgrades
06/12/11    Electrical Selection
21/11/11    Permit Ordered
04/11/11    Land Settlement
03/11/11    Colour Selection appointment
02/11/11    Engineering Drawings Signed
31/10/11    BASIX Approval
27/10/11    Water Board Approval
20/10/11    Building Contract appointment & building contract signed
04/10/11    Tender signed
29/09/11    Tender Appointment
22/09/11    Soil report
19/09/11    Contour survey conducted
12/09/11    Initial deposit